LogCabinMobileHomes-65x22FT-MonoPitch

LogCabinMobileHomePlans8

SPECIFICATION

 

FRAME MATERIALS

 

  • Structural timber to be Scandinavian softwood from sustainable sources graded to comply with our consulting engineers requirements.

 

  • Timber treated with preservative in accordance with BS 5268 Part 5 1976 to comply with current Building Regulation requirements.

 

  • Sheathing to be 9mm thick OSB (orientated strand board).

 

  • Structural fixings to be rust proofed.

 

  • All timber and wood based products on this contract will be FSC/PEFC certified.

 

EXTERNAL WALLS

 

  • Manufactured in panels 2400mm nom high 50 x 150mm finished (38 x 140mm stud at 600mm max centres clad with 9mm OSB sheathing).

 

  • Breather membrane to BS4016 1966 pre-fixed to panels at works with nylon tape to indicate stud positions. The breather membrane will be extended at the sides and bottom of panels to form sufficient laps

 

  • Apertures in panels have lintels and cripple studs as specified by our engineer.

 

INTERNAL WALLS

 

  • Manufactured as panels 2400mm nom high 38 x 89mm stud at 600mm max centres with restraining noggins as required.  Apertures formed as required with all necessary lintels and cripple studs incorporated in panels.

 

  • When walls occur along the central axis of the unit they will be manufactured No.2 x 38x69mm studs walls joined together allowing for separation.

 

PLASTERBOARD SUPPORTS AND ADDITIONAL STUDS

 

  • Additional noggins or studs pre-fixed in panels to provide support for plasterboard at all junctions.

 

  • All necessary additional support studs (below trimmers, beams etc) pre-fixed in panels and marked for precise location on site.

 

GABLE PANELS

 

  • Manufactured as external or internal walls to match roof profile.

 

CHASSIS AND FLOOR

 

  • NORMAL DOMESTIC LOADING

 

  • The floor will be constructed using a primary chassis (to each half of the structure) comprising Glulam beams that will be pre-drilled for connection on site.

 

  • The secondary floor construction will be 18mm OSB chipboard supported by 50 x 150 joists at 600mm max. centres.

 

  • Insulation in the floor zone will be provided by 100mm Kingspan (or similar) insulation with reflective foil held in place by 25x40mm battens.

 

ROOF COMPONENTS  

 

  • The roof construction will comprise 65x225mm T&G solid timber structural decking supported by a composite glulam ridge beam. This supports a 1000g polythene vapor barrier secured by 25x50mm battens at 600mm centres with Super Quilt 14 reflective foil insulation stretched tightly and secured by a further layer of 25mm battens supporting 11mm OSB deck (ready for felt and batten, excluded).

 

  • 32 x 200 PSE unpainted softwood fascia

 

  • 32 x 150 unpainted softwood bargeboard

 

FIXINGS AND SUNDRY MATERIALS

 

  • All necessary nails, bolts, connectors and fixings provided.

 

  • PVA adhesive provided for tongues on chipboard floors.

 

INSULATION

 

  • The roof will be insulated with SuperQuilt 14 reflective foil (as above).

 

  • The floors will be insulated with 75mm Kingspan insulation (as above).

 

  • The external wall insulation, 140mm thick fiberglass.

 

INTERNAL LININGS

 

  • 12mm foil back plasterboard, Fitted.

 

  • 12mm Moisture resistant plasterboard for bathrooms.

 

  • Tape and Joint finish throughout.

 

  • Painted Magnolia and White.

 

ELECTRICS

 

  • 1st and 2nd Fix Electrics.

 

  • Supply and connect 17th edition consumer unit to current regulations.

 

  • Supply wire and fit 13x twin sockets (white).

 

  • Supply wire and fit 4 x single sockets (white).

 

  • Supply wire and fit 2 x bathroom extract fans.

 

  • Supply wire and fit in Kitchen area 4 x Twin sockets, 4 x spurs, 1x cooker controller to kitchen.

 

  • Supply wire and fit 8 x pendant lights and switches (white).

 

  • Wire for no. 2 x outside lights (wiring only).

 

  • Supply wire and fit 1 x spur/isolation switch for boiler.

 

  • Supply wire and fit 9 x panel heaters with individual timers and thermostats (2 x 2.0kw    3 x 1.25kw 1 x 75kw) in White.

 

  • Supply wire and fit 2 x oil filled electric towel radiators to bathrooms (wall mounted chrome finish).  

 

 

PLUMBING

 

  • 1st Fix Plumbing.

 

  • Supply and fix 220ltr hot water cylinder.

 

  • Local connection of Soil Pipes/Vents.

 

  • Bathroom cold feed to toilet. Hot and Cold to Hand Basin. Hot and Cold to Bath Mixer Taps. Feed for overhead shower.

 

  • En-suite cold feed to toilet. Hot and Cold to Hand Basin. Hot and Cold to Bath Mixer Taps. Hot and Cold for overhead shower.

 

  • Sink, Bath, Shower and Taps all included. Style TBC.

 

  • Tiled Floor, Half Wall and Splash Back.

 

INTERNAL JOINERY

 

  • 9 no single  semi solid core moulded panel doors hung on loose pin butts complete with architraves and satin anodised lever furniture

 

  • 25 x 150 moulded skirting.

 

  • Softwood window surrounds and window boards to all windows

 

EXTERNAL CLADDING

  • The building will be clad externally with planed 25mm thick Siberian Larch board on board at width of 125 and 120mm fixed to 25mm battens at 800mm centres (un-finished).

 

FLOOR FINISH

 

  • Natural Oak Engineered Flooring.

 

WINDOW AND DOORS

  • Fitted External Windows and doors as per drawing GL0913-3

 

  • UPVC Plastic. White. Low E-Glass. White handles. Obscured Glass in Bathrooms. Standard Thresholds. Flag Hinges. Multi-point locking.

 

  • Ten Year Warranty all windows/doors (under 180cms wide).

 

KITCHEN

 

  • Fully Fitted Kitchen to Max PC Sum of £5000. Style TBC.

 

DRAWINGS AND ENGINEERING

 

  • 3 full sets of drawings; floor plan, four side elevations and profile.

 

  • Full engineering calculations provided by a 3rd party structural engineer demonstrating (a:) the structure can be split in two stand alone divisible sections (b:) the structure can be lifted with crane and cradle as a whole and also in two separate halves.