LogCabinMobileHome – Dartmoor

LogCabinMobileHomeDartmoor

Specification / Scope of Works Overview

 

 

Structure

  • Timber-Frame Structure. 89mm CLS Internal and External Stud Walls.
  • 2x Engineered Glulam Beam Timber Chassis.
  • Secondary Fabricated Steel Chassis with Wheel
  • 18mm T&G Chipboard over 200x50mm Floor Joists.
  • Pitch Roof with 100x50mm Joists. Vaulted Ceiling.

 

Exterior

  • 9mm External Ply Boarding
  • Felt Breather Membrane.
  • 19x38mm Timber Batten.
  • Horizontal Running Untreated Cedar Cladding.
  • 18mm Roof Decking.
  • Roof Finish in Metrotile Metal Profile Sheet. Black.
  • Galvanized Steel Rainwater Good.
  • Soffitt and Fascia Boards, Cedar.
  • Aluminum Clad Softwood Windows and Doors. Rationel. www.rationel.co.uk

 

Interior

  • 100mm Glass-Wool Insulation for External Walls and Ceiling.
  • Glass-Wool Insulation (or Celotex) for Floor (between joists in timber chassis).
  • Internal Vapor Barrier. Ventilation.
  • Plasterboard or MDF Dry Lining.
  • Internal decorating. Matt Emulsion.
  • All Plumbing 1st, 2nd Fix and Commission Test
  • All Electrics 1st, 2nd Fix and Commission Test
  • White Finish Sockets, Switches and Spot Lights. Low Energy.
  • Solid Oak Laminate Flooring.
  • Internal Doors, Natural Oak Veneer.
  • Painted MDF Skirting and Carpentry.
  • Fitted Bathroom; Toilet (duel flush), Sink (Bathstore)
  • Tiles on Bathroom Floor, Shower and Sink
  • Fully Fitted Compact Kitchen (Howdens)
  • Kitchen Sink, Hob and Oven, (Bosch, Low Energy).
  • Gas Fired Boiler (Worcester Greenstar 25si/30si) with Radiators

 

Delivery

  • Full Delivery, Positioning and Site Equipment.

 

Exclusions

  • Decking.
  • Furnishings.

 

Build Budget Overview

 

Client: James Cole

Site:  Vixon Tor

 

Ground works                                                                         Total £. 9090.00

 

Clear site                                                           £  1800.00

Site reduce                                                         £  800.00

 

Foundations                                                       £ 00.00

Piles (extra)                                                        £ 00.00

Specialist foundations (extra)                                 £ 00.00

Substructure block work                                       £ 240.00

Ground bearing slab                                             £ 5850.00

Precast concrete floor                                            £ 00.00

 

Foul water drainage                                              £ 200.00

Surface water drainage                                           £ 200.00

Water rejuvenation  (extra)                                    £ 00.00

 

Service ducting                                                                        Total £ 00.00

 

Water                                                                £ N/A

Electric                                                              £ N/A

Gas                                                                   £ N/A

Oil                                                                    £ N/A

Garage supply  (extra)                                           £ N/A

Garden Supply (extra)                                           £ N/A

Entrance Supply (extra)                                         £ N/A

Superstructure                                                                                    Total £ 16500.00

 

Timber frame                                                      £ 16500.00

Masonry labour                                                   £ 00.00

Brick                                                                 £ 00.00

Block                                                                £ 00.00

Stone work                                                         £ 00.00

Raw materials, sand, cement, Lintels, ties etc           £ 00.00

Rendering                                                          £ 00.00

Features (extra)                                                   £ 00.00

 

Glazing & Doors                                                                     Total £ 11000.00

 

Wooden                                                             £ 00.00

UPVC                                                               £ 00.00

Screens  (extra)                                                    £ 00.00

Conservatory (extra)                                             £ 00.00

 

Roof Construction                                                                  Total £ 4000.00

 

Felt, Batten and Tile                                            £ 00.00

Flat roofing                                                        £ 00.00

Lead work                                                          £ 00.00

 

Page 1

Insulation                                                                                Total £ 2000.00

 

Loft                                                                   £ 00.00

Floor                                                                 £ 00.00

External wall                                                      £ 00.00

Sound insulation                                                 £ 00.00

 

Electrician                                                                               Total £ 3000.00 pc sum

 

1st fix house                                                        £ 00.00

Garage   (extra)                                                    £ 00.00

Garden   (extra)                                                    £ 00.00

External lighting (extra)                                        £ 00.00

2nd fix house                                                       £ 00.00

Specialist items   (extra)                                        £ 00.00

 

Plumbing                                                                                 Total £ 7000.00 pc sum

 

Under floor heating  (extra)                                    £ 00.00

Central heating system                                         £ 00.00

Boiler supply                                                      £ 00.00

Sanitary ware installation                                      £ 00.00

Hot & Cold Supply                                             £ 00.00

Rain water goods                                                 £ 500.00

Specialist lead work                                             £ 00.00

 

Dry lining                                                                                Total £ 3000.00 pc sum

 

Plaster boarding  (extra)    £ 6.00 per m2                 £ 00.00

Tape & jointing              £ 3.00 per m2                 £ 00.00

Skimming                      £ 8.00 per m2                 £ 00.00

Artexting                                                           £ 00.00

Coving                                                              £ 00.00

 

Ground floor finish                                                                 Total £

 

65mm Screed = 135mm floor finish   £ 18.00 per m2  £ 00.00

Chipboard floating floor = 98mm floor finish            £ 00.00

 

1st fix Carpentry                                                                      Total £ 500.00

 

Nogins for plaster board                                        £ 00.00

Roof carpentry                                                     £ 00.00

Facsia & Soffit                                                    £ 500.00

Internal door linings                                             £ 00.00

Window boards                                                   £ 00.00

Service boxing                                                    £ 00.00

Wardrobes & Cuboards partitioning                        £ 00.00

 

2nd fix Carpentry                                                                     Total £ 6400.00

 

Skirtings                                                            £ 300.00

Architraves                                                         £ 100.00

Internal door hanging inc. Ironmongery                   £ 1000.00

Stairs                                                                £ 00.00

External finishing                                                            £ 00.00

Cladding                                                            £ 5000.00

Page 2

 

Kitchen                                                                                   Total £ 2000.00 pc sum

 

White goods                                                       £ 00.00

Utility provision                                                 £ 00.00

Kitchen provision                                                            £ 00.00

Bathrooms                                                                              Total £ 600.00 pc sum

 

Sanitary Ware                                                     £ 00.00

Vanity Units                                                       £ 00.00

Specialist showers and accessories  (extra)                £ 00.00

 

Decoration and Internal Finishes                                            Total £ 4500.00 pc sum

 

External Painting                                                 £ 00.00

Internal Painting                                                  £ 1000.00

Floor Tiling                                                       £ 400.00

Wall Tiling                                                        £ 600.00

Wet rooms                                                         £ 00.00

 

Specialist floor coverings                                      £ 2500.00

 

Garage                                                                                     Total £

 

Ground works                                                     £ 00.00

Superstructure                                                     £ 00.00

Trusses & roof makeup                                         £ 00.00

Felt, Batten and Tile.                                           £ 00.00

Flat Roof                                                           £ 00.00

Carpentry                                                           £ 00.00

Garage door                                                        £ 00.00

Service door                                                       £ 00.00

Electrics                                                             £ 00.00

Decoration                                                          £ 00.00

 

Landscaping                                                                            Total £ 4000.00 pc sum

 

Earth works                                                        £ 00.00

Soil preparation                                                   £ 00.00

Turfing                                                              £ 00.00

Planting                                                             £ 00.00

Drive makeup                                                     £ 00.00

 

Drive finish                                                        £ 00.00

 

Entrance Provision                                               £ 00.00

 

Fencing & Gates                                                 £ 00.00

Retaining walls                                                   £ 00.00

Patio provision                                                   £ 4000.00

Mobility Access                                                  £ 00.00

 

 

 

 

 

Page 3

Site preliminarys                                                                                 Total £ 2500.00

 

Security Fencing                                                 £ 200.00

Tree Protection provision                                      £ 00.00

Waste removal                                                    £ 300.00

Scaffolding                                                         £ 2000.00

Welfare facilities                                                  £ 00.00

 

Toilet                                                                £ 00.00

Canteen                                                             £ 00.00

Drying room                                                       £ 00.00

First aid provision                                               £ 00.00

Site signage                                                        £ 00.00

 

Service Connections                                                                            Total £ 5000.00

 

Gas                                                                   £ 00.00

LPG                                                                  £ 00.00

Oil                                                                    £ 00.00

 

Electric                                                              £ pc sum 500.00

Telecommunications                                            £ 00.00

Water                                                                £ pc sum 500.00

Septic tank or cesspool                                         £ 00.00

Sewage connection                                               £ 00.00

Sewage treatment plant                                         £ 4000.00

Road Crossing                                                    £ 00.00

 

Miscellaneous                                                                                     Total £

 

Additional architectural fee’s                                  £ 00.00

Structural Engineers fee     £40-50.00 per hr.             £ 00.00

Soil Survey                                                        £ 00.00

Planning Consultant                                            £ 00.00

Quantity surveyor                                                £ 00.00

Project Manager                                                  £ not included

Other                                                                 £

Other                                                                 £

 

Contingency required                                                                          Total £

Total Budget                                                                £

 

Unit fixed                    £ 34000.00

Unit pc sums              £ 26500.00

Unit combined                        £ 60500.00

External & misc           £ 20590.00