LogCabinMobileHome-40x20ft-Scott

LogCabinMobileHome-40x20FT-Scott

£46,500 

 

SPECIFICATION

 

FRAME MATERIALS

 

  • Structural timber to be Scandinavian softwood from sustainable sources graded to comply with our consulting engineers requirements.

 

  • Timber treated with preservative in accordance with BS 5268 Part 5 1976 to comply with current Building Regulation requirements.

 

  • Sheathing to be 9mm thick OSB (orientated strand board).

 

  • Structural fixings to be rust proofed.

 

  • All timber and wood based products on this contract will be FSC/PEFC certified.

 

EXTERNAL WALLS

 

  • Manufactured in panels 2400mm nom high 50 x 150mm finished (38 x 140mm stud at 600mm max centres clad with 9mm OSB sheathing).

 

  • Breather membrane to BS4016 1966 pre-fixed to panels at works with nylon tape to indicate stud positions. The breather membrane will be extended at the sides and bottom of panels to form sufficient laps

 

  • Apertures in panels have lintels and cripple studs as specified by our engineer.

 

INTERNAL WALLS

 

  • Manufactured as panels 2400mm nom high 38 x 89mm stud at 600mm max centres with restraining noggins as required.  Apertures formed as required with all necessary lintels and cripple studs incorporated in panels.

 

  • When walls occur along the central axis of the unit they will be manufactured No.2 x 38x50mm studs walls joined together allowing for separation.

 

PLASTERBOARD SUPPORTS AND ADDITIONAL STUDS

 

  • Additional noggins or studs pre-fixed in panels to provide support for plasterboard at all junctions.

 

  • All necessary additional support studs (below trimmers, beams etc) pre-fixed in panels and marked for precise location on site.

 

GABLE PANELS

 

  • Manufactured as external or internal walls to match roof profile.

 

CHASSIS AND FLOOR

 

  • NORMAL DOMESTIC LOADING

 

  • Timber Chassis Construction. Primary chassis (to each half of the structure) comprising 135mmx220mm Timber Beam. Bolted to allow separation.

 

  • The secondary floor construction will be 22mm OSB chipboard supported by 45 x 195 joists at 400mm max. centres with 9mm OSB sheathing underneath.

 

  • Insulation in the floor zone will be provided by 150mm Glass-wool insulation.

 

ROOF COMPONENTS 

 

  • The roof construction will comprise 45x145mm Roof Joists supported by a composite Glulam ridge beam in 2x Halves 86x225mm. 15mm OSB deck. Felt and Batten.

 

  • 32 x 200 PSE softwood fascia

 

  • 32 x 150 softwood bargeboard

 

  • Metro Light Composite Stone Coated Steel Roof Tiles. Fitted. Black.

 

  • UPVC Rainwater Goods.

 

FIXINGS AND SUNDRY MATERIALS

 

  • All necessary nails, bolts, connectors and fixings provided.

 

  • PVA adhesive provided for tongues on chipboard floors

INSULATION

 

  • The roof will be insulated with 150mm Glass-wool insulation.

 

  • The floors will be insulated with 200mm Glass-wool insulation.

 

  • External walls will be insulated with 150mm Glass-wool insulation.

 

  • Internal walls will be insulated with 100mm Glass-wool insulation.

 

INTERNAL LININGS

 

  • 12mm foil back plasterboard, Fitted.

 

  • 12mm Moisture resistant plasterboard for bathrooms.

 

  • Tape and Joint finish throughout.

 

  • Decoration in Dulux Paint colour of choice (EXCLUDED).

 

ELECTRICS

 

  • 1st and 2nd Fix Electrics.

 

  • Supply and connect 17th edition consumer unit to current regulations.

 

  • Supply wire and fit 10x twin sockets (white).

 

  • Supply wire and fit 6 x single sockets (white).

 

  • Supply wire and fit 1 x bathroom extract fans.

 

  • Supply wire and fit in 1 x Kitchen area 4 x Twin sockets, 4 x spurs, 1x cooker controller to kitchen.

 

  • Supply wire and fit 30 x ceiling down lights (white).

 

  • Wire for no. 2 x outside lights.

 

  • 6 x Electric Radiators with individual thermostats.

 

PLUMBING

 

  • 1st and 2nd Fix Plumbing.

 

  • Supply and fit combination boiler. Electric System.

 

  • Local connection of Soil Pipes/Vents.

 

  • Supply wire and fit 1 x oil filled towel radiator to bathrooms (wall mounted chrome finish).  

 

  • Bathroom cold feed to toilet. Hot and Cold to Hand Basin. Hot and Cold to Bath Mixer Taps.

 

EXTERNAL CLADDING

  • The building will be clad externally with planed 21mm thick T&G Siberian Larch.

 

WINDOW AND DOORS

  • Fitted External Windows and Doors as per drawing 1032-1A

 

  • Double Glazed Factory Painted Softwood Timber Windows and Doors.

 

  • Ten Year Warranty all windows/doors (under 180cms wide).

 

FLOOR FINISH

 

  • Oak Veneered Engineered Flooring Throughout.

 

INTERNAL CARPENTRY

 

  • MDF Skirting and Doors Surrounds Painted White.

 

  • Oak Veneered Internal Doors with Chrome Handles.

 

TOILET AND BATHROOMS

 

  • Toilets, Shower Unit, Bath and Sinks, Standard White (Excluded).

 

  • Tiled Floor and Half Tiled Walls, Splash Back and Surrounds (Excluded).